Wairoa District Council
Forecast capital expenditure by purpose and activity
All figures in $000s, sum of all years ended 30 June 2019 - 2028.
to meet additional demand | to improve levels of service | to replace existing assets | total capital expenditure | |
---|---|---|---|---|
Flood Protection | - | - | - | - |
Roads and Footpaths | - | 7,139 | 54,488 | 61,628 |
Sewage Treatment | - | 2,615 | 8,063 | 10,678 |
Stormwater Drainage | - | 1,803 | 1,426 | 3,229 |
Water Supply | - | 509 | 3,896 | 4,405 |
- Source
- The Council's 2018-2028 Long-Term Plan.