Close Window

Chatham Islands Council

Forecast capital expenditure by type

All figures in $000s, as at year ended 30 June 2019 - 2028.

 2019202020212022202320242025202620272028
Flood Protection - - - - - - - - - -
Roads and Footpaths 3,496 2,588 2,582 2,463 2,275 3,179 2,393 2,345 3,072 2,233
Sewage Treatment - 238 112 - - - 103 - - -
Stormwater Drainage - - - - - - - - - -
Water Supply - 3,384 163 115 36 37 38 40 41 43
Other Activities 910 285 2,407 - 47 - - - 1 1
Total Capital Expenditure 4,406 6,495 5,264 2,578 2,358 3,216 2,534 2,385 3,114 2,277

Source
The Council's 2018-2028 Long-Term Plan.